Find npv for the project if required return is given


A firm evaluates all of its projects by applying the NPV decision rule. A project under consideration has the following cash flows:

Year    Cash Flow
0        -$ 28,600
1            12,600
2            15,600
3            11,600

What is the NPV for the project if the required return is 11 percent?

At a required return of 11 percent, should the firm accept this project?

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: Find npv for the project if required return is given
Reference No:- TGS0550485

Expected delivery within 24 Hours