Explain the different ways a project may be terminated


1. What is a WBS? Explain it's purpose. Describe benefits of using it.

2. What is meant by Gantt chart? Determine the Critical Path and how is it used?

3. Develop simple task schedule network (MS Project is not required but preferred). (Minimum of 15 tasks.) Content is up to you. Minimum needs are as follows: predecessor/successor relationships, duration, task description, start date, end date.

4. Write down the Triple Contraints and why they are significant to understand?

5. Explain the different ways a project may be terminated. Describe the main duties of termination manager?

 

Request for Solution File

Ask an Expert for Answer!!
Project Management: Explain the different ways a project may be terminated
Reference No:- TGS032668

Expected delivery within 24 Hours