Examine the performance of two projects


Examine and compare the performance of following 2 projects in terms of cost, schedule, and efficiency. Ensure to illustrate your computations and analyze and describe the results. (Note: Providing just numbers will earn you only partial credit.)

Project A: The EV is $48,000, and the actual cost is $52,000. The PV is $54,000.

Project B: The EV is $108,000, and the actual cost is $200,000. The PV is $232,000. 