Estimate the electric power available from the plant


At a hydroelectric power plant, the water pressure head is at a height of 300 m and the water flow available is 100 m3 s-1. If the turbine generator efficiency is 60%, estimate the electric power available from the plant (g= 9.8 m s-2).