1. Four hundred and eighty minutes of production time are available per day. The schedule calls for the production of 80 units per day. Each unit of the product requires 30 minutes of work. What is the theoretical minimum number of workstations?

2. Identify a company that was once exclusively a product company but now offers services in addition to products. Briefly summarize the company's product and service offerings and suggest the possible rationale for the service offering.