Discuss the following project situations using just the


Discuss the following project situations, using just the following schedule and cost information: a. PV = $10,000, AC = $12,000, EV = $10, 500 b. PV = $10,000, AC = $10,000, EV = $10,000 c. PV = $10,000, AC = $9,000, EV = $10,000 d. PV = $10,000, AC = $10,000, EV = $9,000.