Develop a wbs for a local stage play


Chapter

Develop a WBS for a local stage play. Be sure to identify the deliverables and organizational units (people) responsible. How would you code your system?

Give an example of the work packages in one of your cost accounts. Develop a corresponding OBS which identifies who is responsible for what.

Larson ( ). Project Management: The Managerial Process . Kindle Edition.

Your roommate is about to submit a scope statement for a spring concert sponsored by the entertainment council at Western Evergreen State University

(WESU). WESU is a residential university with over 22,000 students. This will be the first time in six years since WESU sponsored a spring concert. The entertainment council has budgeted $40,000 for the project. The event is to occur on June 5th. Since your roommate knows you are taking a class on project management she has asked you to review her scope statement and make suggestions for improvement. She considers the concert a resume-building experience and wants to be as professional as possible. Below is a draft of her scope statement. What suggestions would you make and why?

WESU Spring Music Concert

Project Objective

To organize and deliver a 6-hour music concert

Deliverables

• Concert security
• Contact local newspapers and radio stations
• Separate beer garden
• Six hours of musical entertainment
• Design a commemorative concert t-shirt
• Local sponsors
• Food venues
• Event insurance
• Safe environment

Milestones

1. Secure all permissions and approvals
2. Sign big-name artist
3. Contact secondary artists
4. Secure vendor contracts
5. Advertising campaign
6. Plan set-up
7. Concert
8. Clean-up

Technical Requirements

1. Professional sound stage and system
2. At least five performing acts
3. Restroom facilities
4. Parking
5. Compliance with WESU and city requirements/ordinances
Limits and Exclusions

• Seating capacity for 8,000 students.
• Performers are responsible for travel arrangement to and from WESU.
• Performers must provide own liability insurance.
• Performers and security personnel will be provided lunch and dinner on the day of the concert.
• Vendors contribute 25 percent of sales to concert fund.
• Concert must be over at 12:15 A.M.
Customer Review: WESU

Larson ( ). Project Management: The Managerial Process (Page 124). . Kindle Edition.

He provided these as help for Chapter 4 Question 5. Also the other attachmwnt.

https://www.youtube.com/watch?v=V_B-OYNtRM8

Chapter

3. Below is a project WBS with cost apportioned by percents. If the total project cost is estimated to be $600,000, what are the estimated costs for the following deliverables?

a. Design?
b. Programming?
c. In-house testing?
What weaknesses are inherent in this estimating approach?

Larson ( ). Project Management: The Managerial Process (Page 151). . Kindle Edition.

Solution Preview :