Determining the current carrying cost of redan manufacturing


Problem:

Redan Manufacturing uses 3,100 switch assemblies per week and then reorders another 3,100. The relevant carrying cost per switch assembly is $13.00, and the fixed order cost is $1,550.

Required:

Question 1: What is the current carrying cost?

Question 2: What is the order cost?

Question 3: Calculate the economic order quantity.

Note: Please show how you came up with the solution.