Determine the value-added non-value-added total lead times


Question: Please show how you got the answers.

Calculate Lead Time. Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows:

Process Step 1 5 minutes
Process Step 2 8 minutes
Process Step 3 4 minutes
Process Step 4 3 minutes

The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials to Process Step 1 is also 5 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 5 minutes.

The new lean layout will allow the company to reduce the batch sizes from 45 units to 3 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same.

Determine the value-added, non-value-added, total lead times, and the value-added ratio under the present and proposed production approaches. If required, round percentages to one decimal place.


Present Approach Proposed Approach
Value-added time
______min
_____min
Non-value-added time
______min
_____min
Total lead time
______min
_____min
Value-added ratio (as a percent)
______%

_____%

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Determine the value-added non-value-added total lead times
Reference No:- TGS02547378

Now Priced at $15 (50% Discount)

Recommended (96%)

Rated (4.8/5)