Determine the timing of purchase orders part-period method


Assignment:

A manufacturer buys a certain part in varying quantities throughout the year. Ordering cost is $11 per order, and holding cost is $0.14 per unit per month. Given the following demand (net requir e ments) for the part for the next eight months, determine the order sizes and timing of purchase orders using the part-period method.

Month    Demand (Units)
  1.            _
  2.           80
  3.           10
  4.           30
  5.            _  
  6.           30
  7.            _
  8.           30