Determine the slack time for each activity to identify the


Determine the slack time for each activity to identify the critical path for the project.

A building construction company was awarded a project. The project manager has been very concerned with the amount of time it took to complete several recent jobs. The company only has eight labourers available per day for this project and the concern is whether this resource allocation will be sufficient to complete the project on time. The data (all in days) for the new contract are listed in the following table:

Activity

Immediate Predecessor

Duration

Labour Available/Day

A

------

2

2

B

------

4

5

C

------

2

3

D

------

5

2

E

A, B

2

4

F

C, D

3

2

G

D

6

2

H

C, E

3

3

I

F, G, H

5

2

J

E, H

9

4

Solution Preview :

Prepared by a verified Expert
Management Information Sys: Determine the slack time for each activity to identify the
Reference No:- TGS01570094

Now Priced at $5 (50% Discount)

Recommended (92%)

Rated (4.4/5)