Determine the revised completion time for project


Activity Immediate Predecessor (Time Weeks)

A - 1
B A 4
C A 3
D B 2
E C ,D 5
F D 2
G F 2
H E, G 3

a) Sketch the project network.

b) How many weeks will it take to finish the project?

c) Which activities have slack, and how much?

d) Determine the revised completion time for project if duration of activity E is 3 weeks?

Request for Solution File

Ask an Expert for Answer!!
Project Management: Determine the revised completion time for project
Reference No:- TGS031917

Expected delivery within 24 Hours