Determine the project payback period


Problem: You are considering a project with an initial cash outlay of $80,000 and expected free cash flows of $20,00 at the end of each year for 6 years. The required rate of return for this project is 10 percent.

1. What is the project`s payback period?

2. What is the project's NPV?

3. What is the project's PI?

4. What is the project's IRR?