Determine the probability that the project


1. Using the information given in the following table: (A) Identify the critical path. (B) Determine expected project duration.

Activity

Precedes

Duration

Start

A,b,c

-

A

D

5

D

F

6

F

G

2

B

E

5

E

F

9

C

H

4

H

G,i

6

G

End

3

I

End

1

2. Given the network diagram below, determine the probability that the project will finish within 26 weeks of its start. Times on the diagram are in weeks.

3. Use the following to answer questions 3a and 3b

3a. What is the estimated expected (mean) time for activity E?

3b. What is the estimated standard deviation in the time for activity E?

Request for Solution File

Ask an Expert for Answer!!
Basic Statistics: Determine the probability that the project
Reference No:- TGS0837165

Expected delivery within 24 Hours