Determine the level of employment


Problem: DAT, Inc. needs to develop an aggregate plan for its product line.  Its relevant data is given below:

Production Time    1 hr/unit                     Beginning Inventory    500 units
Std Labor Cost      $10/hr                        Safety Stock              1000 units
Overtime              150%   
Workweek            5 days, 8 hrs/day        Shortage Cost             $20/unit/month
Days/Month          20                              Carrying Cost             $5/unit/month

Demand forecast is given in the table below:

Month

Demand (units)

 

January

2500

February

3000

March

4000

April

3500

May

3500

June

3000

July

3000

August

4000

September

4000

October

4000

November

3000

December

3000


If management wants a constant workforce and to limit overtime to 10 hrs/employee/week, determine the level of employment which minimizes cost

Make any necessary assumptions.

Solution Preview :

Prepared by a verified Expert
Other Management: Determine the level of employment
Reference No:- TGS02012749

Now Priced at $25 (50% Discount)

Recommended (97%)

Rated (4.9/5)