Determine the cost of the land and the cost of the building


Martin Buber Co. purchased land as a factory site for $468,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months.

The company paid $49,140 to raze the old buildings and sold salvaged lumber and brick for $7,371. Legal fees of $2,165 were paid for title investigation and drawing the purchase contract. Martin Buber paid $2,574 to an engineering firm for a land survey, and $79,560 for drawing the factory plans. The land survey had to be made before definitive plans could be drawn. Title insurance on the property cost $1,755, and a liability insurance premium paid during construction was $900. The contractor's charge for construction was $3,205,800. The company paid the contractor in two installments: $1,404,000 at the end of 3 months and $1,801,800 upon completion. Interest costs of $170,000 were incurred to finance the construction.

Determine the cost of the land and the cost of the building as they should be recorded on the books of Martin Buber Co. Assume that the land survey was for the building.

Cost of land $
Cost of building $

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Determine the cost of the land and the cost of the building
Reference No:- TGS0717140

Expected delivery within 24 Hours