Q: A garden equipment manufacturer has a product that it makes which is represented by the following product structure tree along with other pertinent data. Use this information and the included editable MRP table worksheet to determine a complete material requirements plan for the 5 week planning horizon Your answer must be presented in the tables included below ABC-51 X (3 P (4 (2 Inventory Records File Lead Time On Hand Lot Size Safety Stock Sched. Receipt Item LAL ABC-51 15 LAL 12 P 1 100 140 in wk 1 53 10 LAL 30 10 28 wk 1 20 10 x 2 25 40 0 Master Production Schedule (Weeks) Product ABC-51 75 50

241_Record file.jpg

            Master Production Schedule(Weeks)

Product   1   2  3    4
ABC-51    0   0  50   0

Horizon Period 1 2 3 4 5 6 7 8 9
Item: Lot siz

LT:

SS:

Gross Requirements
  

  

     
Scheduled Receipts








Projected on hand








Net Requirements








Planned order receipts








Planned order releases







459_Lot Size.jpg

1786_Lot Size.jpg

Request for Solution File

Ask an Expert for Answer!!
Other Subject: Determine a complete material requirements
Reference No:- TGS02030114

Expected delivery within 24 Hours