Critical path-pert calculation


Question: A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before day ________ (rounded to nearest day).

a) 833
b) 807
c) 1009
d) 689
e) 631

Explain in one sentence why please.

Solution Preview :

Prepared by a verified Expert
Microeconomics: Critical path-pert calculation
Reference No:- TGS01616909

Now Priced at $20 (50% Discount)

Recommended (97%)

Rated (4.9/5)