Critical path methodology allows managers to focus on a


1. Critical path methodology allows managers to focus on a group of tasks within a project. What is a potential disadvantage of this methodology?

2. When crashing a project, a manager generally focuses on which activities first?

3. Task C has two immediate predecessors, tasks A and B. Task A has an early finish time of 3 days, and task B has an early finish time of 5 days. Task C is 2 days long. What is the early finish time of task?

4. Task E has an early start time of 3 days and an early finish time of 5 days, while it also has a late start time of 10 days and a late finish time of 12 days from now. What is the slack in task E?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Critical path methodology allows managers to focus on a
Reference No:- TGS02889896

Expected delivery within 24 Hours