Construct the precedence diagram assign tasks according to


A shop works 400 minutes a day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table.

1. Construct the precedence diagram.

2. Assign tasks according to the most following task rule. Break ties with the greatest potential weight rule.

3. Assign tasks according to the greatest potential weight rule. Break ties with the most following tasks rule.

4. Compute the balance delay for each rule. Which one yields the better set of assignments in this instance?

Note: Please do not copy and paste answers from Chegg, I have not found any satisfactory answers to this question here.

Please show all the steps.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Construct the precedence diagram assign tasks according to
Reference No:- TGS02485391

Expected delivery within 24 Hours