Construct the direct labor budget


Response to the following problem:

The production manager of Rordan Corporation has submitted the following of units to be produced by quarter for the upcoming fiscal year:

 

1st Quarter

2nd Quarter

3rd Quarter

4th Quarter

Unit to be produce

8,000

6,500

7,000

7,500

Each unit requires 0.35 direct labor-hours, and direct laborers are paid $12.00 per hour.

Required:

1.Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workface is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

2.Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is not adjusted each quarter. Instead, assume that the company's direct labor workforce consists of permanent employees who are guaranteed to be paid for at least 2,600 hours of work each quarter. If the number of required directed labor-hours is less than this number, the workers are paid for 2,600 hours anyway. Any hours worked in excess of 2,600 hours in quarter are paid at the rate of 1.5 times the normal hourly rate for directlabor.

 

Solution Preview :

Prepared by a verified Expert
Cost Accounting: Construct the direct labor budget
Reference No:- TGS02074505

Now Priced at $25 (50% Discount)

Recommended (93%)

Rated (4.5/5)