Construct a network information


Question 1: Construct a network information from the information in the following table and identify all the paths in the network, compute the length of each, and indicate the critical path.

Activity    Activity Predecessor Time (Weeks)
1   -     7
2   -     10
3   1     6
4   2     5
5   2     4
6   3.4     3
7   5.6     2

Question 2: Determine the earliest start and finish times, latest start times, and slack for each activity. Indicate how the critical path would be determined from this information.

Solution Preview :

Prepared by a verified Expert
Other Management: Construct a network information
Reference No:- TGS01997856

Now Priced at $20 (50% Discount)

Recommended (94%)

Rated (4.6/5)