Consider the following tasks that must be assigned to four


Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task.

Time to Complete Task (seconds):

Task 1:  26

Task 2: 25

Task 3:  15

Task 4: 19

Task 5: 15

Task 6: 20

Task 7: 52

Task 8:  15

Task 9: 20

Task 10:25

Task 11: 15

Task 12: 20

The current conveyor--paced assembly--line configuration assigns the workers in the following way:

• Worker 1: Tasks1, 2, 3

• Worker 2: Tasks 4, 5, 6

• Worker 3: Tasks 7, 8, 9

• Worker 4:  Tasks 10, 11, 12

Assume a demand rate of 13 units per minute. What would be the target manpower?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Consider the following tasks that must be assigned to four
Reference No:- TGS01679591

Expected delivery within 24 Hours