Consider the following information in choosing among the


Question: Checklist. Consider the following information in choosing among the four project alternatives below (labeled A, B, C, and D). Each has been assessed according to four criteria:

• Payoff potential

• Lack of risk

• Safety

• Competitive advantage

Construct a project checklist model for screening these four alternatives. Based on your model, which project is the best choice for selection? Why? Which is the worst? Why?