Assume that the following criteria relevant to the process


Problem: Screening Model.

Assume that the following criteria relevant to the process of screening various construction project opportunities are weighted in importance as follows: Safety (10) Speed to completion (5) Sustainable development (4) Infrastructure modifications (3) Traffic congestion (5) Cost (8) Our company has four project alternatives that satisfy these key features as follows:

1512_Midtown.png

Construct a project screening matrix to identify among these four projects the most likely candidate to be implemented.