Consider a two-station segment of an electronics assembly line. the first station consists of an automated machine that takes an average of 5.1 minutes to process a job. the machine is subject to failure so 20 percent of the jobs drop out after the first station. the second station is a manual operation staffed by a single operator who takes on average 5.7 minutes to inspect each job. there are no failures at the second station. jobs arrive to this segment of the first station at a rate of 10 jobs per hour.

a) Compute the capacity of each station

B) Compute the utilization of each station and determine the bottleneck of this assembly line (hint: rd of the first station= ra of the first station)

c) If a job stays at the second station for 7.2 minutes on average, what is the work-in-process lesvel at the second station on average?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Consider a two-station segment of an electronics assembly
Reference No:- TGS01273296

Expected delivery within 24 Hours