Consider a project having the following ten activities what


Question - Consider a project having the following ten activities:

Optimistic Most likely Pessimistic

Immediate Time (o) Time (m) Time (p)

Activity Predecessors (weeks) (weeks) (weeks)

A none 1 5 9

B A 6 6 6

C A 3 5 9

D A 2 4 6

E B, C 4 4 4

F D 4 7 8

G E 2 2 8

H E, F 7 8 9

I F 4 6 9

J G, H, I 3 5 7

What is the expected time for each activity?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Consider a project having the following ten activities what
Reference No:- TGS02599596

Now Priced at $25 (50% Discount)

Recommended (94%)

Rated (4.6/5)