Compute the takt time for a system where the total time per


Compute the takt time for a system where the total time per shift is 360 minutes, there is one shift, and workers are given 3 10-minute breaks and 30 minutes for lunch. Daily demand is 341 units. (Round your answer to 2 decimal places.)

Takt time             minutes per cycle