Compute the cost variance and classify it as favorable


BatPro makes metal baseball bats. Each bat requires 1 kg. of aluminum at $20 per kg. and 0.50 direct labor hours at $16 per hour. Overhead is assigned at the rate of $40 per labor hour. Assume the actual cost to manufacture one metal bat was $54. Compute the cost variance and classify it as favorable or unfavorable.