Problem: The master scheduling team at a plant producing steel chain is considering a lot-for-lot policy instead of batching into larger lots. The following is their partially completed analysis for 3 levels of chain making (final chain making, fed by fabrication of cut steel pieces, fed by purchased steel rods).

1) Complete the lot-for-lot analysis