Company uese a job-order cost system


The work in progess account for Monty's Company contained the following entries:

Debit of $40,000 for direct raw materials
Debit of $60,000 for direct labor
Debit of $30,000 for manufacturing overhead
ending balance $42,000 associated with Job #2

The company uese a job-order cost system. Work was only performed on two jobs during the period. What was the cost of Job?