Calculates the project duration and identifies the critical


SerDoc is a company that manufactures customised medical equipment for hospitals and is about to initiate a project for building a new machine for a recent order from a hospital. The project involves the following six phases: initiating, requirements gathering, design, development and testing, documentation, deployment and testing. The project is scheduled to start on 15 October.

The duration and precedence relationships (or sequencing) between the tasks of the project are provided in the table below:

Phase

Task Name

Task ID

Immediate Predecessor

Time (Days)

Initiating

Defining the scope of the project

1


5

Initiating

Analysing the existing product which is being produced by SerDoc

2


10

Requirements Gathering

Preparing the requirements document and a high-level design

3

1, 2

15

Requirements Gathering

Conducting a proof of concept to validate the approach

4

3

7

Requirements Gathering

Signoff of requirements and a high-level design from the customers who have ordered the machine

5

3

4

Design

Design of hardware components

6

5, 4

20

Design

Detailed product specifications

7

5

30

Design

Detailed program design*

8

7

20

Development and Testing

Manufacturing of the shell of the machine

9

7, 8

40

Development and Testing

Assembling of the electronic components of the machine

10

7

10

Development and Testing

Testing of the circuit for accuracy of responses

11

9, 10

40

Development and Testing

Testing of the manufactured machine and calibration to standards

12

11

15

Documentation

Preparing an installation and user manual

13

Finishes with 8, 12

30

Deployment and Testing

Installation of the machine at the hospital

14

12

5

Deployment and Testing

Conducting trials and checking all functionality at the hospital after installation

15

12, 14

10

Deployment and Testing

Getting client signoff

16

13, 15

0

Deployment and Testing

Training hospital technicians for using the machine

17

12

15

Deployment and Testing

Commissioning of the machine at the hospital

18

8

9

Part

On the basis of the above information, use Microsoft Project to create a project plan that lists project tasks, establishes precedence relationships between tasks, sets precedence relationships, calculates the project duration, and identifies the critical path. While preparing the project plan, categorise the project tasks in the different phases of initiating, requirements gathering, design, development and testing, documentation, and deployment and testing.

What is the end date of the project?