Calculate the spi and cpi


Problem 1: Imagine that the team planned to complete 30 story points in iteration, but only completed 25. Calculate the SPI.

Problem 2: The earned value to date is $2.2M and the actual costs to date is $2.8M, Calculate the CPI.

Problem 3: Now inform how the project is going?

Request for Solution File

Ask an Expert for Answer!!
Project Management: Calculate the spi and cpi
Reference No:- TGS03290944

Expected delivery within 24 Hours