Calculate the schedule variance schedule performance index


Your project to obtain charitable donations is now 32 days into a planned 42-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $23,000. Even though we are 32 days into the project, we still see that we have only 88% of this activity complete. The second activity relates to company donations and is scheduled to run for 32 days starting on day 7 and extending through day 39. We estimate that even though we should have (25/32) 78% of this activity complete, it is actually only 52% complete. This part of the project was scheduled to bring in $148,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $46,000. So far $177,000 has actually been brought in on the project.

Calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index. (Negative values should be indicated by a minus sign. Do not round intermediate calculations. Round your dollar amounts to the nearest whole number. Round your "performance index" values to 3 decimal places.)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Calculate the schedule variance schedule performance index
Reference No:- TGS02448246

Expected delivery within 24 Hours