Calculate the processing load and develop the load profile for the computer assembly process. As the planner, what concerns do you have (if any)? What changes might you consider?
|
Part Name: Computer
|
|
Processing time 5
|
Week
|
Week
|
Week
|
Week
|
Week
|
Week
|
Week
|
Week
|
|
2 hours
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
|
Planned order releases
|
60
|
50
|
40
|
35
|
70
|
55
|
45
|
60
|
|
Processing load (hours)
|
|
|
|
|
|
|
|
|
|
Available capacity (hours)
|
120
|
120
|
120
|
120
|
120
|
120
|
120
|
120
|