Calculate the processing load and available capacity and


Calculate the processing load and available capacity and develop the load profile for a dishwasher. Eight employees work the assembly process for 40 hours per week each. As the planner, what concerns do you have and what changes would you make (if any)?

Part Name: Dishwasher

Processing time 5

Week

Week

Week

Week

Week

Week

Week

Week

30 minutes

1

2

3

4

5

6

7

8

Planned order releases

600

625

640

600

620

690

645

620

Processing load (hours)

 

 

 

 

 

 

 

 

Available capacity (hours)

 

 

 

 

 

 

 

 