Calculate the overall risk factor for this project


Problem: Quantitative Risk Assessment: Assume the following information:

Probability of failure

Maturity = .3

Complexity = .3

Dependency = .5

Consequences of Failure

Cost = .1

Schedule = .7

Performance = .5

Calculate the overall risk factor for this project.

Would you assess this level of risk as low, moderate, or high? Why?