Calculate the net present value npv for this


Suppose? you're presented with a proposal for a project that costsn?$4200 and will bring in ?$20100 the first year. The next? year, you'll have to pay out ?$15800. With a cost of capital of 14?%, calculate the net present value? (NPV) for this project.

The NPV of the project is