Calculate the expected npv would you build the


An auto plant that costs $100 million to build can produce a line of flexfuel cars that will produce cash flows with a present value of $140 million if the line is successful but only $50 million if it is unsuccessful. You believe that the probability of success is only about 50%. You will learn whether the line is successful immediately after building the plant.

a-1. Calculate the expected NPV. (Do not round intermediate calculations. A negative amount should be indicated by a minus sign. Enter your answer in millions.)

a-2. Would you build the plant?

Yes

No

Suppose that the plant can be sold for $95 million to another automaker if the auto line is not successful.

b-1. Calculate the expected NPV. (Do not round intermediate calculations. A negative amount should be indicated by a minus sign. Enter your answer in millions rounded to 1 decimal place.)

b-2. Would you build the plant?

Yes

No

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Calculate the expected npv would you build the
Reference No:- TGS02699728

Expected delivery within 24 Hours