At december 31 2015 seasons construction estimates that it


At December 31, 2015, Seasons Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $14,400,000 due to unanticipated price increases. What is reported in the balance sheet at December 31, 2015 for Seasons as the difference between the Construction in Process and the Billings on Construction in Process accounts, and is it a debit or a credit? Difference between the accounts Debit/Credit a. $3,380,000 Credit b. $1,240,000 Debit c. $880,000 Debit d. $1,240,000 Credit Please show how are you getting your answer.