Assuming BCC uses the percentage-of-completion method of recognition the gross profit recognized in 2013 would be (rounded to the nearest thousand):

$42,000.

$6,000.

$45,000.

$39,000.

Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2013, are presented below:

Bid price

 

 

$450,000   

Contract cost:

 

2012

(180,000)

 

 

2013

(195,000)

Gross profit:

 

 

75,000   

 

 

 

 

Estimated cost to complete:

 

 

12/31/2012

$200,000

 

 

12/31/2013

0

 

 

Assuming BCC uses the percentage-of-completion method of recognition the gross profit recognized in 2013 would be (rounded to the nearest thousand):

$42,000.

$6,000.

$45,000.

$39,000.

Assuming BCC uses the percentage-of-completion method of recognition the gross profit recognized in 2013 would be (rounded to the nearest thousand):

$42,000.

$6,000.

$45,000.

$39,000.