1. Assume you are on the marginal case curve…if the desired throughput for the operation is a minimum of 450 units and customers need the product in no longer than 3 days, you could deliver these results by:

a. Reduce WIP to 100 units

b. Reducing WIP to 1500 units

c. Increasing WIP to 2800 units

d. None of the above

2. If the operation had no variability, it could achieve a TH of 800 units and a cycle time of less than 0.5.

a. True

b. False