Asmall rm is considering to upgrade its assembly line


A small rm is considering to upgrade its assembly line. It takes 8 hours for the current system to assemble a unit of product. The system can make 3 units of product per hour After the upgrade, it takes only 4 hours to assemble a unit of product. The system still makes 3 units per hour. What is the reduction of inventory? (Hint: calculate the number of computers being assembled in the system before and after the upgrade.)