Analyze and compare the performance


Analyze and compare the performance of the following two projects in terms of cost, schedule, and efficiency. Make sure to show your calculations and analyze and explain the results. (Note: Providing just numbers will receive only partial credit.)

Project A: The budgeted cost of work performed is $72,000, and the actual cost of work performed is $75,000. The budgeted cost of work scheduled is $73,000.

Project B: The budgeted cost of work performed is $48,000, and the actual cost of work performed is $100,000. The budgeted cost of work scheduled is $122,000.