An assembly line pulls containers of parts from machining


An assembly line pulls containers of parts from machining centers at a rate of 600 per day. Each container holds 20 parts and typically waits 2 hours at a machining center before it is processed. The setup and process time for 20 parts is 6 hours. How many containers are needed if the safety margin is 10%?