An assembly line makes two models of trucks a buster and a


An assembly line makes two models of trucks: a Buster and a Duster. Busters take 12 minutes each and Dusters take 8 minutes each. The daily output requirement is 24 of each per day. Develop a perfectly balanced mixed-model sequence to satisfy demand.