An assembly line at the Yokohama Plant in West Point has 22 tasks is to be balanced to produce a special variety of tires. The longest task is 5.6 minutes, and the total time for all tasks is 27 minutes. The line will operate for 480 minutes per day. What is the minimum number of workstations needed if the maximum output rate is to be sought?