An activity has an early start es of day 3 a late start ls


An activity has an early start (ES) of day 3, a late start (LS) of day 13, an eary finish (EF) of day 9, and a late finish (LF) of day 19. The activity:

A) Is on the critical path B) Has a lag C) Is progresssing well D) Is not on the critical path