A suitcase manufacturing company needs to but certain type


A suitcase manufacturing company needs to but certain type of specialized machinery to for production. The long term estimated annual demand is about 60,000 suites. If one suitcase requires 10 minutes of production time, and company runs factory for 100 hours per week, how many machines will be needed? (one year = 50 weeks) If 20% capacity cushion is required, how many machines will be needed?