A skilled worker believed to be on a 90 learning curve


A skilled worker, believed to be on a 90% Learning Curve, produced for the first unit of the item no X235 in 75 minutes. According to your calculations, the same worker should be able to produce the unit # 12 of X235 in approximately:

a. 49 minutes b. 75 minutes c. 51 minutes d. 31 minutes